A venue contract required a promoter to pay $20,000 if it canceled a scheduled concert. At contracting, the venue's lost profits and rebooking costs were difficult to estimate, and $20,000 was a reasonable forecast of likely loss. The promoter canceled and argues that the clause is an unenforceable penalty.
Which statement is most accurate?